Sunday, June 1, 2008
Thursday, May 22, 2008
Drywall
Thursday, May 8, 2008
Forward Progress
Thursday, April 17, 2008
Green With Envy...No, It's Just The Termite Treatment
This week's progress includes adding all of the exterior doors, completing the brick veener, and istalling the fireplace insert.
View of the Kitchen with the termite treatment. The entire first floor is sprayed with this stuff.
View of the front with a freshly graded lot, front door, and the brick veneer.
The garage has been back-filled and tamped. I will let the ground settle for a week or two and then poor the floor.
Brick veener on back corner of the house behind the master bedroom.
Side view of garage with entry door.
Close-up of the front door.
Walk out basement with french door.
Back of the house with brick veneer, the back door, and the deck frame.
Sunday, April 6, 2008
Continued Progress
The roof was completed Thursday. I used 30 year architectural shingles. All of the windows have been set in place as well. The doors are scheduled to be set Monday.
All rough HVAC, Plumbing, and Electrical work was completed last week
1st floor HVAC ducts and wiring
2nd floor air-return
2nd floor unit
HVAC ducts in basement
1st floor HVAC unit in basement
Brick Mason working on the front of the house